Border-to-Border Pathway Segment D3 Project Update #15
On To Paving...
April 29, 2024
Finally, paving of Segment D3 of the Border-to-Border Trail along the Huron River in Scio Township has begun!
Over the last couple of weeks, the contractor has driven steel piles for the bridge abutments and placed the base course of asphalt along some portions of the trail. Next, the contractor will be placing forms for the concrete bridge abutments to prepare for placing the pedestrian bridge. Once the bridge is set in place, asphalt paving of the remaining portions of the pathway will continue.
As a reminder, the pathway remains closed to the public...
READ MORE